info
Electrical energy' is precious, Start to save energy today. Dont postpone for tomorrow..! -Consumer Facilitations Portal

Tariff Structure

04896-263709 [Consumer Care]

നിലവിലെ താരീഫ് നിരക്കുകള്‍

Tariff Structure

Existing FY 2016-17

I-Phase Energy Charges(Rs/kWh) Fixed Charges III-Phase Energy Charges (Rs/kWh) Fixed Charges
BPL/Kutir Jyoti --- Rs25/month/connection
Domestic
0-100 units  1.3

Rs. 15 /connection/permonth for I phase connection

 1.3

Rs. 50 /connection/per month for III phase connection

101-200 units  3  3
201-300 units  4.85  4.85
301 units & above  6.3  6.3

Commercial

0-100 units  6.05 Rs. 25/connection/per month for I phase connection  6.05 Rs. 100/connection/per month for III phase connections
101-200 units  7.3  7.3
201 units and above  8.55  8.55

Commercial (Gov. Consumers)

0-200 units   6.60 Rs. 25/connection/per month for I phase connection   6.60 Rs. 100/connection/per month for III phase connections
201 units and above  7.70  7.70

Commercial

HT(High-Tension) Consumers

8.4 Rs. 100 /kVA/month 8.4 Rs. 100 /kVA/month

Industrial

5.8 Rs. 35 /kVA/month 5.8 Rs. 35 /kVA/month

Public Lights

5.3 Rs. 0 /kVA/month 5.3 Rs. 0 /kVA/month

Temporary Connections

10.2 Rs. 0 /kVA/month 10.2 Rs. 0 /kVA/month

Air Conditioner Surcharge

0 0

Meter Rent Charges

10 25

Connection Charges

250 500

Reconnection Charges

50 100

Service Connection Initial Charges

Rs. 250 - I Phase Rs. 500 - III Phase Rs. 1000 - HT

BPSC (%)

10 2

Meter Testing Charges

Rs. 100 Rs. 300

Meter Card

5 0

Meter shifting charges(premises)

Varying Rs. 1000

Shifting of Poles (On request)

----- Rs. 1500

Diversion of LT/HT Line

  Rs. 100/meter

Penalty for Tampering supplier equipments

----- As per JERC supply code.

Installation Testing charges

Rs. 10 - I Phase D Rs. 50 - I Phase C Rs. 50 Public Rs. 25 - III Phase D Rs. 100 - III Phase C Rs. 250 - III Phase I Rs. 50 Public